Estonian energy companies challenge Elering’s new grid tariffs for battery storage
Six Estonian energy companies have raised objections to changes in transmission grid tariffs scheduled to take effect on 1 January 2027, warning that higher capacity-based charges could discourage investment in battery storage.
The tariff structure, approved by Estonia’s competition regulator in September, shifts a greater share of network charges towards installed capacity rather than electricity transmission. Battery operators are particularly exposed because they are exempt from certain energy-based network charges.
According to the companies, the new structure will make battery storage projects less competitive in Estonia. Enery has also pointed to Lithuania, where it says network charges for battery storage are considerably lower.
Elering chief executive Kalle Kilk defended the changes, arguing that battery operators must contribute to the costs of maintaining the network. He said granting them additional preferential treatment would shift those costs to other customers.
Energy and Environment Minister Erkki Keldo acknowledged the competing concerns and said the ministry was looking for a balance between investment incentives and Elering’s need to recover network costs. No decision to amend the approved tariffs has been announced.