Soli LT Connects 402 MWh Battery Park to Lithuania’s 330 kV Grid

LithuaniaStarted

Lithuanian electricity transmission operator Litgrid has connected the first stage of UAB Soli LT’s battery storage park in Šilutė district to the national transmission network.

The system has an installed power capacity of 201 MW, a permitted generation capacity of 150 MW and a storage capacity of 402 MWh. The batteries have already started storing and supplying electricity to the grid.

Litgrid describes the facility as Lithuania’s largest battery park to date and the country’s first standalone energy storage facility connected to the 330 kV transmission network.

Lithuania already has battery storage installations with a combined capacity of 2.98 GWh across its transmission and distribution networks. Soli LT plans to expand the park’s storage capacity to 1,000 MWh by the end of 2027.

The project adds to Lithuania’s storage-first power strategy.